    四川省小宝鼎煤矿38号煤层采动垮落带、导水裂缝带特征及发育高度研究

    Study on the characteristics and development height of the Caved Zone and water-conducting fracture zone in mining No.38 coal seam at Xiaobaoding coal mine, Sichuan province

    • 摘要: 以小宝鼎煤矿12383工作面为工程依托,综合运用经验公式预测、钻孔窥视实测与数值模拟三类技术手段,系统探究38号煤层采动后垮落带及导水裂缝带的发育特征。结果显示:经验公式预测得出垮落带、导水裂缝带最大发育高度分别为8.23 m、35.30 m;钻孔窥视实测获得二者最大发育高度依次为9.19 m、37.10 m;数值模拟计算得出的垮落带、导水裂缝带最大发育高度则为9 m、40 m。三类方法所得结果具有良好一致性。取得的成果可为煤矿制定矿井防治水工作方案及水害安全风险管控措施提供依据。

       

      Abstract: This research takes the 12383 working face of Xiaobaoding Coal Mine as the engineering background. It systematically explores the development characteristics of the caved zone and water-conducting fracture zone in the No.38 coal seam after mining through a comprehensive application of three technical methods: empirical formula prediction, borehole peeping measurement, and numerical simulation. The results show that: the maximum development heights of the caving zone and water-conducting fracture zone predicted by empirical formulas are 8.23 m and 35.30 m, respectively; the maximum heights obtained by borehole peeping measurements are 9.19 m and 37.10 m in sequence; and the maximum heights calculated by numerical simulation are 9 m and 40 m. The results obtained by the three methods are in good agreement. The research results can provide a basis for coal mines to formulate mine water prevention and control plans and safety risk management and control measures for water hazards.

       

    /

    返回文章
    返回